July 2012
The Pools Working Group presents its position paper. The rough concept includes the reconstruction of the indoor swimming pool, envisaged as a pure "sports pool", and the renovation of the outdoor pool. A combined pool is proposed, integrating the outdoor and indoor pool areas. After examining five possible locations, the location at Sternbusch is recommended for the new pool.
-
-
-
August 2012
The supervisory board recommends implementation of the planned combined pool at the Sternbusch location to the city council of Kleve. The supervisory board further recommends to the council that a positive advance ruling should be obtained from the tax authority in relation to tax consolidation, which will significantly reduce the costs of the combined pool.
-
-
-
September 2012
The council approves the concept of the combined pool at the Sternbusch location as proposed by the supervisory board. The approval is made subject to a positive ruling by the North Rhine-Westphalia (NRW) tax authority regarding tax consolidation. The supervisory board is to assist in further detailed planning.
-
-
-
November 2012
The NRW tax authority issues a “ban on rulings”. No applications for advance rulings on tax consolidation will be processed until further notice.
-
-
-
January 2013
The pool operators - with the help of a consultant - begin planning the so-called preliminary draft, in order to create a detailed concept from the outline concept of the working group for the combined pool.
-
-
-
April 2013
The supervisory board is informed of the status of the preliminary draft.
-
-
-
August 2013
The supervisory board debates modifications to the preliminary draft.
-
-
-
November 2013
The supervisory board decides on further modifications to the preliminary draft.
-
-
-
February 2014
Europe-wide call for tender for general planning services for the developed project.
-
-
-
July 2014
Contract for general planning awarded to the GSF planning office. Managing directors Rolf Hoffmann and Christoph Keinemann, GSF (l-r).
-
-
-
August 2014
With the support of the general planner, further development of the preliminary draft from a pure sports pool to a “pool for the whole family, with a sports focus” is examined.
-
-
-
October 2014
The tax authority in NRW lifts the ban on rulings for advance rulings on tax consolidation. Applications for advance rulings can again be processed. However there are now significantly increased requirements placed on the tax consolidation group.
Contract for project management awarded to the CONSTRATA engineering company. Managing director Rolf Hoffmann with Wilhelm Brand and Jens Kerkhoff from CONSTRATA (l-r).
-
-
-
December 2014
Kleve public utilities company make an application to the NRW tax authority for an advance ruling on tax consolidation based on the new requirements.
-
-
-
February 2015
The tax authority issues the positive advance ruling.
-
-
-
March 2015
The Sternbusch outdoor pool is prepared for the 2015 season - for the last time in the old layout.
-
-
-
June 2015
The revised concept for the family pool is approved by the city council of Kleve.
-
-
-
July 2015
The building application is lodged.
-
-
-
September 2015
The last season in the “old” Sternbusch outdoor pool is rounded off with a dog swim. Mayor Sonja Northing and animal photographer Magnus Pomm.
Start of the first tender phase. The construction project is divided into convenient individual projects, so that regional companies also have the opportunity to participate. In the first phase there are 7 EU tenders and 3 restricted tenders.
-
-
-
December 2015
Building permission is granted. The active construction phase can begin.
-
-
-
January 2016
And we're off! The diggers are rolling in and demolition works commence on the outdoor pool with the gutting and dismantling of buildings no longer required.
-
-
-
March 2016
With a groundbreaking ceremony, reconstruction of the Sternbusch pool is under way. Chairman of the supervisory board Jörg Cosar, managing director Rolf Hoffmann, mayor Sonja Northing and project manager Heinz Waskowiak (l-r).
-
-
-
April 2016
After several operations, the bomb disposal team (BDT) ends surface sounding of the building area. For this operation the ground was first stripped layer by layer. With the approval by the BDT, civil engineering works can now be safely resumed.
The first of three cranes is erected and levelling for foundations is completed in some areas.
-
April 2016
The foundation course, lightning protection and supply lines are laid.
-
-
-
Juni 2016
The base plates and the almost 5m-high basement walls and columns are poured.
-
Juni 2016
Before erection of a soldier pile wall – also known as a Berliner wall – sounding holes are drilled to ensure there are no bombs. Architect Philip Keinemann (right) with a member of the bomb disposal service.
-
Juni 2016
Drone flight over the construction site
-
-
-
July 2016
The technical and storage rooms are created at basement level using sand-lime brick masonry.
-
July 2016
The formwork for the family pool is based on these columns and provisional supports. After reinforcements have been laid by the reinforcing iron and rebar workers, the base plate can be poured.
-
July 2016
The formwork for the family pool is based on these columns and provisional supports. After reinforcements have been laid by the reinforcing iron and rebar workers, the base plate can be poured.
-
-
-
August 2016
The base plate of the family pool has been freshly poured and is moistened with water for slow hardening.
-
August 2016
The base plates for the sports pool and the teaching pool are created perpendicular to the family pool.
-
August 2016
The teaching pool can be easily identified by its contours. When complete, it will feature an innovative self-supporting movable floor.
-
August 2016
Aerial photographs show the recognisable contours and proportions of the large new indoor swimming pool.
-
August 2016
Aerial photographs show the recognisable contours and proportions of the large new indoor swimming pool.
-
-
-
October 2016
With the aid of a connecting passage, the renovated basement equipment room of the former outdoor pool is linked with the basement of the new indoor swimming pool.
-
October 2016
The concrete walls for the sports pool are almost complete. Afterwards the basement ceiling in the area of the pool border can be closed. To check for leaks, all pools are subsequently filled with water for two weeks.
-
-
-
November 2016
The porch at the entrance and the first walls at ground level are erected.
-
November 2016
Once all of the modules of the air conditioning equipment – each several metres in height – are installed in the basement, the access opening is concreted over.
-
November 2016
This is where the foundations for the two imposing ventilation towers will be laid.
-
-
-
January 2017
This is the current view from crane no. 1.
Kleinkinderbecken = toddler pool
Familienbecken = family pool
Kursbecken = teaching pool
Sportbecken = sports pool
Sanitärbereich = toilet facilities
Umkleidebereich = changing rooms
An dieser Stelle wird ein Ganzjahres-Außenbecken entstehen. = An all-season outdoor pool will be built at this location. -
January 2017
Here we show you the view from crane no. 3 towards the family area.
Eingangshalle = reception
Gastronomie = restaurant area -
January 2017
The perspective from the restaurant area gives the viewer a good spatial representation of the new family area. The room demarcation at the end of the hall offers a view towards the sports and teaching area through the large windows. The partition wall, along with the wooden surfaces in the ceiling and wall area, will in the future contribute to pleasant acoustics.
-
January 2017
View towards the main entrance of the Sternbusch pool. To the right beside the building there will later be entrances for direct access to the outdoor pool.
-
-
-
February 2017
The steel truss assembly is installed. It forms the intricate support structure for the roof of the new combined pool.
-
-
-
April 2017
The roof surface is already closed and will be protected against the elements with the aid of sheeting. In the next step, bituminous sheeting will be laid.
-
April 2017
Here the shell of the all-season outdoor pool can be seen. Later it will be accessible from the family pool through a covered passageway.
-
-
-
May 2017
Celebrating the roofing ceremony! In addition to the greetings and thanks, mayor Sonja Northing and Mr Heinz-Jörg Cosar, chairman of the supervisory board of Kleve public utilities, share with the audience a range of interesting facts about the Sternbusch pool construction project. Please also note the media reports in this regard in the "News" section.
-
May 2017
Celebrating the roofing ceremony! In addition to the greetings and thanks, mayor Sonja Northing and Mr Heinz-Jörg Cosar, chairman of the supervisory board of Kleve public utilities, share with the audience a range of interesting facts about the Sternbusch pool construction project. Please also note the media reports in this regard in the "News" section.
-
May 2017
After the ceremonial speech by Mr Meissner, foreman of the van Stephoudt company, the audience applauds as the wreath is raised up on a crane.
-
-
-
June 2017
Ventilation channels are laid in the basement of the new indoor swimming pool.
-
-
-
July 2017
The concrete structure of the all-season outdoor pool is complete. In the next steps, the bubble loungers will be installed and the tiles fitted.
-
-
-
August 2017
Beside the steps to the family pool, the frame for the bubble loungers is complete. Now the formwork for the lounger surfaces will be laid and the concrete poured.
-
-
-
September 2017
The walls of the sports pool are already fully tiled. In the next step the overflow channel of the pool rim will be put in place. The floor tiles will then be laid in a thick-film process.
-
September 2017
The new diving pool will be constructed in the outdoor area. Starting with installation of the overflow channel, the main body of the pool will then be overlaid from top to bottom with stainless steel.
-
-
-
November 2017
Glazing of the north and east façade of the new indoor swimming pool is almost complete. The building is now protected against the elements. With the aid of the heating system - operated on a provisional basis - work on the interior can be continued and completed.
-
November 2017
The tiled teaching pool. The screed for the pool border was subsequently applied and can already be walked on. Installation of the movable floor is planned for December.
-
November 2017
Tiling of the family pool is already at an advanced stage. Afterwards the pool border will be treated with screed.
-
November 2017
In the redesigned multipurpose pool in the outdoor pool area, the indent on the right-hand side provides an interlock for safely exiting the famous wave slide. Installation and welding work on the stainless steel pool can only be carried out in good weather. For quality assurance purposes, samples of the material used are tested and the works supervised by a technical expert.
-
-
-
January
The extensive bathing water technology is located in the basement. The image shows e.g. the pipes leading to and from the family and the corresponding splash-water tanks. The splash-water tanks are used to store water pushed over the pool edge by visitors, and which flows over the overflow gutter on the pool edge.
-
-
-
February
Work on the façade of the new indoor swimming pool is complete - except for the porch area.
-
February
The car park in the northern section of Sternbusch Swimming Pool is being redesigned. After laying the drainage pipe and lighting cables, the base layers are now being installed and compacted.
-
-
-
March
As soon as weather permits, work on the outdoor stainless-steel pools will continue. To ensure high quality long-term, e.g. when welding the metal sheets, the outdoor temperature must not fall below 5 degrees centigrade.
-
March
The new kids’ pool will also be stainless steel. The upper bathing level for babies has a suitable depth of 0 to 20 cm. This is linked to the lower toddlers’ pool via a sliding and climbing level. The lower area will have a depth of up to 40 cm.
-
-
-
Aerial view of Sternbusch Swimming Pool from the 6th of May, 2018.
-
The side walls of the outdoor pools have been lined with stainless steel sheets. The distinctive lazy river can be clearly seen in the large, multi-purpose pool.
-
The lime green colour of the lobby at the main entrance clearly distinguishes itself from the elegant grey of the building.
-
This photo shows the perspective of a diver on the 3-metre diving board. The pool will be filled later this month after wall panelling has been completed, and the pool has been thoroughly cleaned.
-
The spacious changing area also features the colour combination of modern grey, lime green and wood.
-
-
-
(R-L) Rolf Hoffmann, Managing Director of Stadtwerke, and Heinz Waskowiak, Bäderbetriebe Project Manager, in front of the stainless steel pool in the outdoor area.
A report by the Federal Institute for Materials Research and Testing (Bundesanstalt für Materialforschung und -prüfung) has confirmed that the installed stainless steel complies with quality standards.
This allows us to continue to use the tested material to construct the pool facilities. -
This photo shows the new outdoor area for our younger guests. Piping for the stainless steel pool was recently completed.
-
-
-
Successful trial – Stadtwerke Kleve illuminates the new Sternbuschbad using green energy
On 29 August, 2018, Sternbuschbad's new lighting concept was put into operation on a trial basis. In the late evening hours, various lighting options were successfully tested for the first time. Meanwhile, work at Sternbuschbad continues at a fast pace. The opening date has not yet been confirmed, but an announcement is expected shortly.
-
-
-
-
-
-
-
The car park in front of the pool entrance was completed in October 2018. When commissioning the new lighting system, we made sure to avoid creating any "fear zones". All areas of the car park are now sufficiently lit.
-
-
-
The grand opening took place on 26 October 2018. "This pool complex was built for the citizens and guests of the city", Stadtwerke Managing Director Rolf Hoffmann emphasised, presenting the key to Mayor Sonja Northing (right).
-
-
-
While visitors enjoy swimming indoors, work continues on completion of the outdoor pool area. Work on the stainless steel pools will soon be completed, followed by paving work and levelling of the terrain.
-
-
-
December 2018
In December 2018, the outdoor pools were filled for the first time. As part of the partial filling process, we checked the tightness and the pools were inspected for leaks. The filled water also served to protect the stainless steel from the oncoming frost.
-
-
-
January 2019
Extensive earthworks began at the start of the new year. The earth that was previously excavated for construction of the interior had been heaped into large mounds. It took about 1,000 truckloads to remove it.
-
-
-
February 2019
Terrain modulation started in February. Many new recreation areas await our guests this summer.
-
-
-
April 2019
Painting and building fitting works are being finalised in the outdoor area. The lawn has now been seeded and more than 100 trees newly planted on the extensive grounds.
-
-
-
-
May
A press conference was held on May 27th, at which the opening date for the outdoor pool area was announced as July 12th 2019.
-
-
-
June 2019
The grass is growing well. The outdoor area will open on July 12th 2019. On this day, normal service for both the indoor and outdoor area will begin at 2pm.
-
-
-
July 2019
On 12 July 2019 the outdoor area of the Sternbusch pool was opened, accompanied by a top-class show program.
After almost three years' construction, from now on residents and guests of the town can use both the indoor and outdoor area of the new Sternbusch pool complex.
Our documentation of the planning and construction phase of this project of the century now comes to an end.
We wish all pool users a sporty and relaxing stay.
Stadtwerke KleveFormer beach volleyball internationals Ilka Semmler and Katrin Holtwick (from left) accepted the invitation of managing director Rolf Hoffmann. They opened the new beach volleyball court with an exhibition match against SV Bedburg-Hau.
-
The "Cologne Bombs" opened the new pool complex with breathtaking dives.
-
The program was rounded off with a performance by Lukas Kepser and band.
-
-
-
Construction diary
After 50 years of operating the Königsgarten indoor swimming pool and almost 40 years operating the Sternbusch water park, in 2011 Bäderbetriebe Kleve hired pool renovation specialists to look into the renovation and remodelling requirements of both pools. The results of the study by the specialist firm were presented to the newly-established "Pools Working Group". The task of the working group was to develop a concept for the future of pool operations in Kleve based on the results of the study. The group was to come up with a recommendation for the political bodies that would meet the future requirements of a modern, needs-based, ecological and economically-viable pool in Kleve that would also provide leisure facilities. With this construction diary, we offer you the opportunity to take a closer look at the progress of this interesting project.
-